What are the types of tunnel lining formwork?

Tunnel lining formwork

The tunnel lining trolley is an indispensable non-standard product for the secondary lining during tunnel construction. It mainly consists of simple lining trolley, full hydraulic automatic walking lining trolley and grid lining trolley. The fully hydraulic lining trolley can be divided into a side arch type, a full round needle beam type, a bottom mold needle beam type, a full circle walking type and the like. Lifting slipforms, jacking slipforms and overturning are also commonly used in hydraulic tunnels and bridge construction. Full-round lining trolleys are often used in hydraulic tunnel construction. Vertical tunnel joints are not allowed in tunnels. Full-circle walk-through type is generally used when the span of hydraulic tunnels is large; the application of side-arched lining trolleys is common. It is commonly used in the secondary lining construction of roads, railway tunnels and underground caverns.

1. Simple lining trolley

The simple lining trolley is generally designed as a steel arch type. It uses a standard composite steel formwork. It can be used without external walking. It is driven by external power. The detaching formwork is all manual operation and labor intensive. This type of lining trolley is generally used for short tunnel construction, especially for tunnel lining construction with complex plane and space geometry, frequent process conversion and strict process requirements, and its superiority is more obvious.

For example, a double-arch tunnel of a highway is 200m long, and the plane is at a circular curve of R=300m. The cross slope in the tunnel changes from i=±2% to +5%, and the tunnel is also at R=3000m. On the vertical curve, the tunnel shape is in a “hyperbolic” state, while the middle wall is a straight wall design. The outlet 15m is gradual from R=5.5m to R=7.5m. The tunnel reinforced concrete is lined with a simple arch. The trolley design is a good solution to these problems, and the engineering cost is low.

Most of the simple trolleys use artificial perfusion rafts, and the simple lining trolleys are filled with sputum pump trucks, so the rigidity of the trolleys should be particularly strengthened. Some simple lining trolleys also use integral steel formwork, but the detachment die still uses the screw rods, and there is no automatic walking. This type of trolley is generally filled with a sputum pump. Simple lining trolleys generally use composite steel formwork. The combined steel formwork is generally made of thin plate. The rigidity of the steel formwork should be considered in the design process, so the spacing of the steel arches should not be too large.

If the length of the steel formwork is 1.5m, the mean spacing of the steel arches should be no more than 0.75m, and the longitudinal joints of the steel formwork should be placed between the concrete and the concrete to facilitate the installation of the formwork fasteners and the formwork hooks. If the pump is used for perfusion, the filling speed should not be too fast, otherwise the combined steel formwork will be deformed, especially when the thickness of the lining is more than 500mm. Care should be taken when filling the cap, and the filling condition of the cockroach should be paid attention to at any time to prevent the cockroach from being forced to fill after filling. Otherwise, the explosion mode or the trolley will be deformed and damaged.

2. Fully hydraulic automatic walking lining trolley

It is mainly used in the construction of medium and long tunnels, and has high requirements on construction progress and surface quality of concrete. This type of lining trolley is designed as an integral steel formwork and a hydraulic cylinder to take off the vertical die. The construction is supported by a screw rod. The electric reducer is automatically driven or the cylinder is stepped automatically. All of them are filled with a pump. Most lining trolleys are such trolleys.

When designing such a lining trolley, in the case of meeting the clearance requirements, the lower installation position of the diagonal support on the inside of the gantry should be considered, as close as possible to the lower part of the column, so that it is well stressed. The gantry beam should be high enough that the conventional railway tunnel is not less than 400mm and the road tunnel is not less than 5500mm. The small distance between the end face of the template and the gantry is not less than 250mm, otherwise the front and back lining sections will be difficult to overlap.

When lining the trolley with this type, it should be noted that the paving height difference between the two sides of the traveling rail is not more than 1%, otherwise the screw jack and the jacking cylinder will be deformed. When lining a tunnel with a ramp, in order to adjust the lining elevation, the height difference between the front and rear ends of the trolley and the end face of the stencil are not parallel with the end face of the gantry, which will cause a large horizontal component between the stencil and the gantry, resulting in a large horizontal component. The support screw between the template and the door frame is misplaced, resulting in damage to the cylinder and the cylinder.

Therefore, in the design, the constraint structure or adjustment system that causes the horizontal component of the front and rear height differences should be fully considered. When positioning the vertical mold, the rail clamp must be installed, tighten the basic screw jack, the top of the gantry and the top of the formwork. If necessary, other measures can be used to reinforce the position of the lower arch, so that the gantry is exhausted. It may be small to prevent deformation of the running mold and the gantry.

3. Net frame lining trolley

The truss lining trolley has been structurally modified compared to conventional lining trolleys. In the construction of the traditional lining trolley, the trolley frame is a force-bearing member. It receives a large side pressure and varies with the stiffness of the gantry. It is not suitable for direct operation in tunnels with large cross slopes and longitudinal slopes. The requirements for the working environment are high, otherwise the overall deformation and damage of the trolley will be caused.

The truss lining trolley frame is unstressed during construction, and the support member of the stencil is the top screw of the side arch, and the gantry is only stressed during the process of taking off the mold and walking, and The force is vertically downward, there is no side pressure, and the gantry is designed to be rigid enough to be deformed according to the weight of the trolley. When constructing or walking in a tunnel with ramps, whether it is a horizontal slope or a vertical slope, the height can be adjusted through the jacking cylinder at the lower part of the gantry, so that the whole trolley is in a horizontal state, and there is no front tilting force in the whole trolley. And the side force ensures the overall stability of the trolley.

Because the trolley completely cancels the screw for support, the trolley is easy to position and can be adjusted to the geometric position of the lining very quickly, saving a lot of manpower and material resources, improving work efficiency, shortening the work cycle, and saving engineering accordingly. cost. In order to ensure the rigidity and strength of the top arch formwork, the upper frame is designed as a grid-type bar structure, so that the force is good, and the template will not be deformed and displaced during the lining process. The weak link in the whole trolley is the lower template and the lower mold supporting the diagonal rod. Therefore, when designing the lower template, the force of the lower mold should be fully calculated, and the width and thickness of the curved plate should be widened as much as possible. The rod is stable and calculated to ensure that the slanting rod has sufficient rigidity and strength to prevent deformation and bending during use, resulting in running the mold. In the calculation process, the influence of the lining thickness, slump, perfusion speed, aggregate size and whether it is reinforced concrete or not should be fully considered.

The screw of the lower arch is the main force-bearing part. When the whole formwork is below the centerline of the center of the lining, it is supported by it. Therefore, the structural form and rigidity should be considered in the design. In use, the jack must be firmly pressed against the ground, no looseness is allowed, and if necessary, it can be reinforced with other parts as an auxiliary support to prevent the running mold and the trolley from shifting downward.

It should be noted that the rails as the longitudinal positioning of the trolley and the basic screw jacks must be tightened, stuck and secured to the rails, especially when lining the ramp. This type of lining trolley is mainly used for the construction of large-span tunnels and underground caverns.

If the traditional full-hydraulic lining trolley is used, the gantry design is difficult to meet the requirements of use, resulting in deformation and damage of the gantry. First, the truss beam is distorted and deformed, eventually leading to running the mold. If the beam is raised, the cross section of the vertical sill, the side sill and the end face are increased, which causes unnecessary waste, and the lining lining trolley can overcome the above difficulties. Since this type of lining trolley is a large-span construction, its operability should be considered in design, and its working ladder and working aisle should be able to reach every working position conveniently.

What is the role of a two-lined trolley?

The second lining trolley refers to the tunnel two lining trolley is an important part of the tunnel construction, the tunnel concrete lining is indispensable construction equipment!
The lining lining trolley is a special equipment that must be used in the secondary lining of the tunnel construction process, and is used for lining the inner wall of the tunnel. The lining lining trolley is an indispensable non-standard product for the secondary lining during tunnel construction. It mainly consists of simple lining trolley, tunnel lining trolley walking system and grid lining trolley. The fully hydraulic lining trolley can be divided into a side arch type, a full round needle beam type, a bottom mold needle beam type, a full circle walking type and the like. Lifting slipforms, jacking slipforms and overturning are also commonly used in hydraulic tunnels and bridge construction.
Full-round lining trolleys are often used in the construction of hydraulic tunnels. Longitudinal joints are not allowed in tunnels. When the span of hydraulic tunnels is large, full-circle-passing is generally used; side-arched lining trolleys are most commonly used. It is commonly used in the secondary lining construction of roads, railway tunnels and underground caverns.
Tunnel lining trolleys The most domestic manufacturers of trolleys should be Luoyang’s manufacturers. Because Luoyang has strong mechanical processing capabilities and professional tunnel construction experience of China Railway Tunnel Bureau, Luoyang tunnel lining trolleys are currently in the domestic market. The occupation rate is very large. The manufacturers of tunnel lining trolleys in China are basically more or less related to Luoyang. So ordering tunnel lining trolleys is completely available in Luoyang. If there is a tunnel lining trolley that needs processing or design drawings, Luoyang’s design plan is absolutely first-class in China, and can also provide on-site technical assistance.

new

Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. is led by the technical elite of the former China Railway Tunnel Group Machinery Factory, the tunnel machinery equipment industry experts and professional sales team. Over the years, the company specializes in tunnel steel formwork lining trolleys, tunnel waterproof board trolleys, tunnel gutter cable trough trolleys, middle partition wall trolleys, inverting arch bridges, inverting arch formwork trolleys, tunnel maintenance trolleys, water conservancy radio stations. Vehicle, single-track railway vehicle steering platform, urban subway city underground pipe lining trolley, various formwork and trolley accessories. The products are distributed in construction sites such as railways, highways, hydropower, urban subways, urban underground pipe corridors, etc., and are highly praised by customers. With the pace of customers, the market has expanded to “One Belt, One Road” to respond to the country. The series products have reasonable structure, advanced technology, convenient installation, high strength, good stability, smooth and smooth template, and easy operation.
“Achieving a Partner and Winning the Future” is the company’s business philosophy. As a tunnel bridge, Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. and the tunnel construction and construction customers shared the mission of sharing the fate, and established the “crossing the Tianzhu to build a tunnel and interconnected the world.” “For the company’s mission. To solve problems in tunnel construction and make construction safer, more efficient and easier, the company regards customer problems as opportunities; sincerely look forward to working with customers to create new technologies and processes for tunnel construction.

Five maintenance methods for tunnel construction lining trolley

Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. is led by the technical elite of the former China Railway Tunnel Group Machinery Factory, the tunnel machinery equipment industry experts and professional sales team. Over the years, the company specializes in tunnel steel formwork lining trolleys, tunnel waterproof board trolleys, tunnel gutter cable trough trolleys, middle partition wall trolleys, inverting arch bridges, inverting arch formwork trolleys, tunnel maintenance trolleys, water conservancy radio stations. Vehicle, single-track railway vehicle steering platform, urban subway city underground pipe lining trolley, various formwork and trolley accessories. Here is a brief introduction to its maintenance methods:

new

(1) The hydraulic oil is replaced after the work of the trolley for 15 working cycles.

(2) Apply butter to the screw jacks in each working cycle to remove the concrete from the gantry, the jack and the surface of the formwork.

(3) The mold release agent must be applied to the template for each work cycle.

(4) The piston rods of each cylinder must be covered when pouring concrete to prevent concrete from falling on the surface of the piston rod.

(5) After each demoulding, check whether the connecting bolts are loose or not. If loose, tighten them. The five-die must fully tighten the coupling bolts to prevent gaps and misalignment between the pallet templates.

Four positioning analysis of lining trolley

Before the lining work, the trolley must be positioned to make the cross-sectional dimensions of the trolley consistent with the required dimensions. After the trolley walks to the section to be lined, it is positioned by the following actions:

new

(1) Adjust the center line of the trolley by operating the translation cylinder of the hydraulic system to align it with the centerline of the tunnel;

(2) Operate the hydraulic system jacking cylinder to raise the trolley to the standard lining height, and then tighten the foundation jack, then review the height dimension;

(3) Operate the hydraulic system so that the lateral cylinder piston rod extends and reaches the standard lining section, and then manually pulls the lateral support screw to make it reach the lateral cylinder support position and tighten;

(4) After completing the above actions, the section size should be reviewed to prevent errors.

Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. is led by the technical elite of the former China Railway Tunnel Group Machinery Factory, the tunnel construction equipment industry experts and professional sales team. The company has more than 30 engineers and senior engineers, more than 300 professional technicians and after-sales service personnel, and more than 50 marketing and management personnel. The company has a construction area of more than 10,000 square meters, and is well equipped for machining, welding, tooling and inspection.

 

Jintai Railway Jiangjunling Tunnel

news

The Jintai Railway Jiangjunling Tunnel has been completed. The Zhejiang Railway Network has added a 10,000-meter long tunnel.

On the morning of December 5, a valley in the junction of Xianju County and Jinhua Chun’an County, dozens of Jintai Railway builders gathered here. The mountain roads are difficult to stop, and they can’t stop their pace; the mountains are winding, but they don’t care about the beauty. After more than 900 days and nights of hard work, the key control project of the Jintai Railway, the Junjunling Tunnel, was completed on the same day. At this point, the heavy mountain of Yokohama no longer blocks the two places.
On January 4, 2016, the groundbreaking ceremony of the Jintai Railway was held in the leading section of the Jiangjunling Tunnel. The builders used the four “most” to describe the project: it was the earliest tunnel in the whole line and the longest tunnel in the whole line; it was the longest tunnel in the whole line, with a total length of 12.808 km; it was the most difficult of the whole line. The tunnel has extremely complicated geological conditions, high environmental protection requirements and difficult transportation.
“Tunnel construction, what we do is to open the road every mountain!” Huang Jiubin, deputy chief engineer of the 3rd project manager of Jintai Railway, used a set of data to illustrate the difficulty of the operation: the temperature of the original rock in the tunnel site can reach up to 39.08 °C. The upper limit of the physical and mental health and working efficiency of the workers specified by the super-standard is 25 °C; the tunnel passes through 20 fault-fractured zones, 5 sections of rock-blasting zones, and 3 sections of shallow-buried biased sections. “Some have to be repaired on cliffs and landslides. The access road can lead to the construction of the hole; some have to repair the river dam in the upper reaches of the river to ensure the safety of the construction during the mountain period.” He cited, for example, the inclined shaft of the tunnel No. 1 to the exit section, due to the large depth of the ground, the development of groundwater, plus Jian Stones, secondary stones and horizontal rock formations are intertwined, which can easily lead to the occurrence of rock bursts, water inrush and slippage.

new

Faced with the construction problems caused by complex geological environment, Jintai Railway Company and the construction side China Railway Tunnel Bureau Group cooperated to develop a scientific research system, and researched and upgraded and applied a number of new technologies and processes. Such as tunnel 3D cross-section detector detection technology, tunnel two-lining anti-cavity detection technology, manipulator spray technology, mobile trestle construction inverting arch filling technology, etc., a number of new processes are the first application here, laying a solid foundation for safe and rapid construction. The foundation has created the highest record for the entire line of continuous excavation footage of more than 220 meters for 6 consecutive months.
The tunnel penetrated the scene, and the same smiles as the builders, as well as the villagers in Putian Village, Hengxi Town, Xianju County. “Go, let’s go and see the tunnel that has been opened.” Several old folks are coming to the helmet and go to the tunnel. It is this road under their feet that will change the history of the railway.
It is reported that since the beginning of this year, various projects of the Jintai Railway have progressed smoothly. The 24 participating units and more than 10,000 builders across the board are full of enthusiasm. In the past two months, seven tunnels, such as Niuheling Tunnel, Jiulong Tunnel, Ziyan Tunnel and Yanxia Tunnel, have been continuously connected. The land acquisition and demolition tasks have been basically completed. The construction of Jintai Railway will be transferred from the offline to the line, and the new one will be opened. Construction chapter.

Luoyang Gaofei went to China Railway Equipment to carry out technical exchanges and cooperation!

news

Luoyang Gaofei and China Railway Equipment (China Railway Engineering Equipment Group Tunnel Equipment Manufacturing Co., Ltd.) are long-term strategic partners. For a long time, they have been interacting with each other and have been promoted. Due to the invitation of China Railway Equipment, when the business managers of various regions returned to the first quarter meeting, on March 28, 2019, our general manager Cheng Chaoliang led the team to bring the business elite. The technical team went to visit and exchange to discuss the cooperation direction and sales policy of tunnel equipment and product related knowledge this year.

The exchange was highly valued by the leaders of China Railway Equipment. Wei Jin, deputy general manager, Cui Wenbin, deputy chief economist, and Wang Bosong, chief technical officer, personally received the visit, learned and exchanged, and cultured, on-site management, product development, and The knowledge of tunnel equipment products and the development of domestic and international markets have gained a deeper understanding.
Since the signing of the strategic cooperation agreement between the two parties in early 2018, the relevant business cooperation has been carried out frequently, which has laid a good foundation for the cooperation between the two parties and has taken the first step of a win-win situation. After friendly talks, the two sides reached a deepening cooperation intention in TBM, shield supporting products, three-arm drilling rigs, wet spray machines, steel arches and other projects, and agreed on the next cooperation policy in future business cooperation.

Warmly celebrate the successful holding of our 2019 second quarter marketing conference

In June, at the end of the middle of the year, in order to sum up the past and clear the goal, our company held the “2019 Second Quarter Marketing Work Conference” at the Group Headquarters from July 1st to 3rd, 2019. This meeting can be said to be a summary. With the report, the training and improvement of peers, achievements and honors, and struggle and determination.

news

In the second quarter, it was the continuation and breakthrough of the “opening the door” activities in the first quarter, and it was also the reaffirmation and shaping of the “quality year” and “image year” of Luoyang Gaofei. Under the leadership of the company, under the correct leadership of the sales manager, under the joint efforts of the three regional managers and all the business staff, the company successfully won more than 58 million and basically completed the sales target for the second quarter of 2019. It also laid a solid foundation for the realization of the annual sales target.

Gao Fei’s sales team is an excellent team and a young team. It is hard-working, energetic, “wolf” and lacking. At the same time, the meeting did not forget to learn. In the past three days, everyone, carefully equipped, carefully reported, a little bit of pieces, there were discussions, reviews, and records; in three days, everyone, serious study, exchanges, there is, there is Training, communication, and improvement. In the past three days, the company has specially explained and trained on product structure explanation and technical communication, how to improve service awareness, professional image and etiquette, managerial quality, financial knowledge and reimbursement process, and specially invited doctoral tutor of School of Mechanical and Electrical Engineering of Central South University. Dean of Gaofei Bridge and Tunnel Intelligent Equipment Research Institute personally develops demand in the competitive market, how to mine customer demand, user core demand, differentiated competitive strategy in quarterly competition stage, tunnel lining trolley construction process, “SPIN” sales method The theory and practice of sales negotiation, negotiation strategy and negotiation skills have been thoroughly explained. The sentence is classic, the words are in the words, and the words are in the words. The words in the lines make our long-lost feelings stronger, and the struggle is stronger. The strength of the lameness is even more…·····. After the meeting, the company also specially held a grand celebration banquet for the sales team. Everyone relaxed their mood and devoted themselves to tomorrow’s “battle.”

news news