Lining trolley technical requirements and acceptance criteria

Tunnel waterproof board laying formwork

In order to improve the quality of tunnel construction and implement the requirements for project management standardization, the design and acceptance criteria of the formwork trolleys are unified. It is required that the tunnel lining formwork trolley adopts a unified structural form and processing technical standard, and is accepted and accepted according to the same acceptance criteria. The processing technical standards and acceptance criteria of the formwork trolley are issued, and the relevant departments are requested to provide the template table according to the following requirements. Car processing plan:

First, the technical standards for tunnel lining trolley processing:

1. The length is designed according to 12m.

2. The profile of the lining section is designed to be 50mm larger according to the contour of the cross section of the attached tunnel.

3. The surface adopts the national standard 10mm cold rolled sheet.

4. The clearance in the gantry should ensure the safe passage of vehicles and personnel in the cave. It is necessary to consider the traversing form of the wind and water pipelines inside the cave, and consider placing them on the lower side of the trolley in parallel. The ventilation pipe is considered to have a diameter of 1.2 m, and a space of 1.4 m is required to be placed and placed on the upper side of the gantry (not placed in the middle).

5. The trolley lifting cylinder stroke, side mold cylinder stroke and traverse cylinder stroke are designed to be 300mm.

6. The working windows are staggered according to the type of characters, the size is 500 mm×500 mm, the layer height is not more than 1800 mm; the vault is arranged with two grouting ports with the same diameter as the concrete pump, and the joints and seals are provided.

7. Lay 200mm × 200mm sleepers on the top of the inner rail at 1060mm and adopt P43 rail design.

8. Lower longitudinal beam: Two I60 I-beams are used to form a group of welded parts; the gantry column is made of I36C I-beam; the upper longitudinal and transverse beams and the middle longitudinal and transverse beams are assembled into two sets of welded parts by two I30a I-beams; The scissors support I20a I-beam. (I60 600 × 190; I36C 360 × 140; I30a 300 × 145; I20a 220 × 110. Data: height × leg width, unit mm).

9. If the material of the above-mentioned 8th trolley is replaced by other materials, the substitute material shall not be lower than the standard in Article 8; the gantry structure, support system and formwork of the formwork trolley shall be guaranteed to meet various construction loads. It has sufficient strength and rigidity to be deformed within the requirements of the Bata Railway and national regulations.

10. The template joints should be tight and not leaking, the surface flatness is not more than 3mm, the seam is not more than 1mm.

11. The width of the panel is not less than 1500mm, and the walking speed of the trolley is about 6m/min.

12. The lining trolley should be provided with sufficient load-bearing screw support and radial formwork screw support.

13. Using full hydraulic positioning, hydraulic system working pressure 16Mpa.

14. The surface is ground and oiled on the basis of the original steel plate; except for the surface of the template, the non-machined surface of all parts is coated with a reddish topcoat.

15. The demoulding method is considered by each manufacturer.

16. The vertical gantry is longitudinally arranged at a spacing of not less than 2 meters.

17. The plug template should be considered in the design and designed separately.

18. The lower part of the outer formwork is hinged at a height of 50 cm, and the lower 50 cm high part can be rotated to the inner side, and the height of the lower edge is not less than 30 cm.

19. The design comes with a walking system.

Second, tunnel lining trolley acceptance criteria

1, the main body part

(1) The structural parts of the skeleton structure are smooth and beautiful, without bending, bending and torsion deformation, the weld placement is reasonable, the thickness of the weld is up to standard, and there is no welding and other welding defects.

(2) After assembly, the bolt holes are basically free of misalignment.

(3) After assembly, the diagonal error of the main door frame is not more than ±5mm, and the verticality of each gantry is not more than 5mm.

2, hydraulic operating system

(1) Each valve and cylinder move freely, and the effective stroke of the cylinder is reasonable.

(2) The piping of the system is arranged reasonably, and there is no oil leakage in each joint.

(3) The top mold, the side mold (or the bottom mold) are demoulded, the position is flexible, and there is no card collision.

3, walking system

(1) The walking system moves freely, without jitter, slipping and the like.

(2) There is no oil leakage in the walking gearbox, and the chain sag is moderate.

4, the template

(1) There is no shortage of welding and desoldering of the single template. The arch plate has no distortion, and the rib plate has no curved panel and has no defects such as rust, convex and concave.

Serial number Project Standard Acceptance method
1 Actual contour and design contour surface arbitrary point normal error ≤3mm Ruler
2 The working window panel and the surface of the template should be in the same arc: wrong platform, gap ≤1.5mm 2m by foot and feeler
3 Diagonal error ≤3mm Ruler
4 Length error ±2mm Ruler
5 Width error ±2mm Ruler
6 Contour surface (arc surface) flatness ≤3mm/2m 2m by foot and feeler
7 Hinged hole position error ≤0.5mm Ruler
8 Hinged hole center line link and template center line perpendicularity error ≤1mm Ruler
9 Web and panel perpendicularity 1.5mm/300mm Ruler

(2) After the template is assembled, the anti-rust paint is sprayed, and the surface treatment is polished before spraying, and the surface of the template is smooth, free from irregularities, no welding slag, burrs, and flash. The template storage, transportation and hoisting are equipped with anti-change measures.

Serial number Project Standard Acceptance method
1 Contour radius ±3mm Ruler
2 Template flatness 3mm/2mm 2m by foot and feeler
3 Template wrong ≤2mm 2m by foot and feeler
4 Template gap ≤1.5mm 2m by foot and feeler
5 Surface roughness Polishing 2m by foot and feeler
6 Longitudinal straightness error of the outer contour surface of the template trolley ≤2mm 2m by foot and feeler
7 From the template vertices, divided by the height of 2m, the chord length and design error ≤ ± 2mm Ruler
8 Front and rear end contour error of template trolley ≤3mm Ruler

(3) Installation tolerance and inspection method for tunnel lining trolley

Serial number Project Standard Acceptance method
1 Side wall corner ±10mm Ruler
2 Arch line ±2mm Ruler
3 Dome ±2mm Level measurement
4 Template surface flatness 4mm 2m by foot and feeler
5 Adjacent casting section surface height difference ±4mm Ruler

5, the work window

(1) The clearance between the hinge pin and the positioning pin is not more than 0.5mm.

(2) The unevenness of the surface of the working window and the surface of the template, that is, the misalignment with the surface of the template is not more than 1 mm.

(3) The gap between the perimeter of the work window panel and the formwork panel is no more than 1mm.

(4) Each work window is opened and closed freely.

6, support system

(1) The bending of each screw can not be greater than 2mm.

(2) The screw is flexible and the effective length of the thread is reasonable.

(3) The overall support system of the trolley is reasonably arranged and there is no weak support zone.

Main structure of tunnel lining trolley template

The tunnel concrete maintenance formwork

The tunnel lining trolley template (hereinafter referred to as the trolley) is mainly composed of the following ten parts: formwork, table beam, gantry, bottom longitudinal beam, walking mechanism, translation mechanism, support system, 8, electrical system, hydraulic system, accessories Wait for ten parts.

1. Template: The template is divided into: a top mold and two side molds. The width of the template is generally 1.5 meters as the basic modulus, so the total length of the trolley is a multiple of 1.5, such as: 6.0, 7.5, 9.0, 10.5 and 12.0 meters. The template is the main image component of the trolley, requiring an accurate, flat, smooth, and error-free outer surface. Therefore, be careful in the process of manufacturing, transportation, installation, use, etc. Can not cause any scratches and distortion. In order to enhance the overall function of the template, the through beam, the column, the hanging beam, the diagonal support, the scissors support and the rib plate are arranged on the inner side of the template to ensure the template is strong.

2. Platform beam: The platform beam is the main load-bearing member of the upper part of the trolley. It is made of heavy-duty I-beam. The lower edges of the two ends of the pedestal are connected by a translation mechanism and a gantry, and the girders are connected into a whole by a hanging beam to form a load-bearing structure.

3. Gantry: The gantry is the skeleton of the trolley, which consists of the door beam, the column, the diagonal bracing and the connecting plate. The bottom is connected with the bottom longitudinal beam, and the upper surface is connected with the platform beam through the translation base. For its stability and reliability, a plurality of auxiliary members such as a lock beam and a scissors support are arranged between the door frames to form a complete frame system. Most of the door beams and columns are welded by steel plates, and the diagonal braces are mostly made of heavy-duty I-beam. It is required to have sufficient strength and rigidity, which is one of the indicators of the quality of the trolley.

4. Bottom longitudinal beam: The bottom longitudinal beam is the overall load-bearing component of the trolley. It requires high strength and high rigidity, and is often welded with heavy-duty I-beams. The upper part is connected with the gantry column, and the lower part is connected with the running mechanism. A screw jack is arranged between the steel rail and the bottom longitudinal beam to ensure good stability.

5. Walking mechanism: The traveling mechanism is composed of a traveling frame, a wheel pair and a power driving device. Its task is the overall load-bearing member of the trolley and the driving device for the trolley walking. It is driven by a motor to drive the cycloid reducer through the chain and the sprocket to make the wheel set forward or backward, complete the walking task, and the driving speed of 8 m / min is safe and reliable.

6. Translation mechanism: The translation mechanism is used to fine-tune the alignment of the trolley after the vehicle is in position, so that the center of the trolley coincides with the center of the tunnel, and the translational cylinder on both ends of the door beam is used to pull the translation base to slide on the door beam to complete the alignment. effect.

7. Support system: All lead screws are support systems, which vary in length and length. Support is an important part of the trolley. It is the main means of fixing the formwork and the support frame. Therefore, each screw has the function of each screw and cannot be simplified. The lead screw has a template supporting lead screw, a template ground supporting the lead screw, a platform beam leg screw and a bottom longitudinal leg leg screw.

8. Hydraulic system: The main task of the hydraulic system is to use the template to lift and retract the position. There is a small amount of support. For example, the lifting master cylinder of the top mold should play a supporting role, sinking to prevent leakage, and set up a machine on the cylinder. Lock, the remaining cylinders are not the main load-bearing components, so there is no mechanical lock or hydraulic lock.

9. Electrical system: The electrical system is composed of distribution box, operation button and cable. It is the power source of the trolley and the control center for various movements of the trolley.

10. Accessories: The accessories for the trolley are: step ladder, fence, work platform, operation table, plugging plate, working window, filling port, inclined shaft trolley with anti-overturning mechanism and so on.

How should the tunnel lining trolley be maintained?

Tunnel concrete maintenance formwork

Tunnel lining trolleys will play a vital role in real life, especially in the use of industry will be able to play their biggest role, of course, often in the process of actual equipment processing, can not be separated from such A product that how to maintain it when it is actually used is something that many people want to know.

1) The tunnel lining trolley must be operated continuously for 15 working days during the maintenance process, and the hydraulic oil inside should be replaced after the cycle.

2) Every work cycle should be buttered to the top of the screw, and for the gantry or the concrete on the stencil and related stencils, be sure to pay attention to effective cleaning.

3) Each mold cycle must be coated with more release agent.

4) If concrete tunneling is to be carried out in a tunnel lining trolley, more piston rods must be covered on top to prevent concrete from falling on the piston rod surface.

5) After each time the tunnel lining trolley is demoulded, the bolts of each component should be effectively checked to see if they are loose. If there is looseness, tighten it. If it is not loose, then Be sure to better prevent the surface from appearing staggered.

Tunnel lining trolley daily use precautions

1. If you want to use the tunnel lining trolley, you must find the relevant operation manual to carry out effective installation and installation before use. All the processes need to check whether each component has a firm link one by one. It depends on their actual installation. In the case, after installation, you must also try again, to see if the rotation of the entire vehicle is flexible. Of course, when the installation is actually carried out, there will be various installation methods.

2. Nowadays, in the actual installation process of the tunnel lining trolley, the relevant position is basically to start the vertical mold. When the switch is started, the operator should cooperate with some other vehicles to install, so that the shape of the whole template can be reached. There is a construction requirement. When the entire formwork meets the construction requirements, the upper and lower templates will be precisely combined, and then the template of the entire tunnel lining trolley will be closed. After the two templates are assembled up and down, the concrete can be poured. By transporting the concrete to the relevant formwork trolley, basically, it is possible to perform better perfusion, and to maintain the balance of the trolley.

3. After the tunnel lining trolley is demoulded, the work can be completed after the strength of the inverted concrete reaches a certain operational requirement.

Tunnel lining trolley This kind of equipment will belong to a unique equipment in real life, and the whole equipment must be paid attention to when using it. It must be maintained and maintained by this professional. Otherwise, if it is true If you want to operate, you should also choose a professional person to operate. Only in this way can you bring better protection to prevent problems later.

Congratulations on our company’s certification of weapons and equipment quality management system

1

In the autumn of September, good news was passed. After the Beijing Air Transport Association’s “GB/T9001-2018 (ISO9001:2008)” quality management system certification, Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. successfully passed the Beijing Aviation Association’s “GJB9001C-2017” weapon. Equipment quality management system certification, which marks that our company has become “the earliest military private enterprise supporting bridge and tunnel equipment in the industry”.

1

This award is not a day’s work. The company is strategically arranged and carefully arranged. Every stage is painstaking and step by step. Every journey pursues quality, pays attention to word of mouth, steadily and steadily, and gradually builds the “Gaofei” brand. After several years of accumulation, after careful preparation by various departments for several months, after several strict reviews, on September 18, 2019, it was finally awarded the national military standard management department and the military industry system safety production standardization evaluation agency – China Aviation Industry Association Certification, and obtain the weapon equipment quality management system certification!

The acquisition of the certificate also marks that our products not only meet the production standards, industry standards, but also meet the military standards! This is a manifestation of our comprehensive strength, and we are proud of it, both glory and responsibility! Regardless of military or civilian use, we always adhere to the principle of “rigorous refinement, innovation and efficiency”. We will continue to develop on the road of development, strictly control the quality, and pledge to make the bridge and tunnel equipment into a fine product, so that the equipment can enjoy the military quality.

I believe that thick accumulation will surely hit the sky, we have been working hard.

Luoyang Gaofei Bridge Tunnel Machinery Co., Ltd. is mainly engaged in full hydraulic steel formwork tunnel lining trolley series, inverted arch trestle, inverted arch trolley, fully automatic waterproof board trolley, ditch cable trough trolley, maintenance trolley, open Digging trolleys and other series, shield machine accessories, various tunnel templates and accessories series required for trolleys.

Website: www.gfqsjx.com
Marketing Department Tel: 0379-80881719 60162687
Central China Manager: Ning Liangliang 15090151463
East China Manager: Huang Jizhen 17630350001
Northeast Manager: Zhang Gaolin 17 737930478
South China Manager: Han Yuchuan 1338387 7199
Southwest Manager: Li Yanlong 13183063064
Northwest Manager: Gong Xinzhuang 18037931638
North China Manager: Song Yizhuo 15194591494
Northwest Manager: Lulo 1372160571

 

What are the technical parameters of the tunnel lining formwork?

Tunnel waterproof board laying formwork

The tunnel lining formwork is a special equipment that must be used in the secondary lining of the tunnel construction process, and is used for lining construction of the inner wall of the tunnel. There are mainly simple lining trolleys, full hydraulic automatic walking lining trolleys and grid-type lining trolleys; full hydraulic lining trolleys can be divided into side-arched arches, full-round needle-beams, bottom die-pins, full circles walk through and so on. Lifting slipforms, jacking slipforms and overturning are also commonly used in hydraulic tunnels and bridge construction.

First. Lining formwork structure

The lining trolley consists of three parts: the frame, the formwork and the hydraulic power system. By hydraulically installing the vertical mold and demolishing the mold, the full-section lining of the tunnel can be completed at one time.

1. Trolley frame

It mainly includes gantry longitudinal beams, beams, columns, diagonal braces, side links, top links and walking parts. In the case of meeting the requirements of strength and rigidity, the steel design is adopted to ensure the structure is reasonable and the processing is simple and rapid. The connection of each component is connected by bolts and knots, which is easy to disassemble and easy to transport.

2. Template

The total length is 12m, divided into 8 segments, each segment is 1.5m long. Each segment consists of two side stencils and two top stencils in the circumferential direction. The entire trolley has a total of 32 templates. Each formwork consists of a panel, a skirt and a rib portion. This structure not only increases the overall rigidity of the formwork, but also increases the weight of the formwork, compared with the use of I-beam and channel steel.

The two top stencils are bolted together, which facilitates the installation, disassembly and adjustment of the stencil. The connection between the top template and the side template is hinged.

3. Support

The template support is divided into two parts: vertical lifting and lateral stretching. The vertical lifting adopts 6 vertical cylinders for lifting and lowering, and the lateral direction uses 6 lateral cylinders for expansion and contraction. The vertical cylinders are flanged and the side cylinders are earrings. After the template is in place, it is supported by a screw jack. This support method ensures that the formwork does not retract or deform when it is lining.

4. Template translation mechanism

There are 2 horizontal hydraulic cylinders on the top of the trolley frame to adjust the lateral position of the template.

5. Subsidiary decoration

The accessory frame includes 6 gantry jacks, 4 top bracket jacks, hydraulic pumping station, walking mounting, workbench, lighting circuit and so on. The hydraulic pump station is designed as a vertical closed structure. The hydraulic pump is placed in the fuel tank, and the multi-way reversing valve is placed above the fuel tank for easy operation and neat appearance.

Second. The main technical parameters

1. Template

The thickness of the panel is 12mm, the skirt is 12mm thick steel plate, and the rib is made of 70×50 angle steel. There are 4 attached vibrators and 4 concrete pouring spouts on the top of the template, and 24 working windows with a size of 500×450. The horizontal adjustment movement of the template is 150mm on the left and right.

2. Hydraulic power system

The pressure is 16 MPa and the flow rate is 14.5 L/min. The vertical cylinder has a cylinder diameter of 160 mm and a stroke of 400 mm with a hydraulic lock. The lateral cylinder has a cylinder diameter of 90 mm and a stroke of 730 mm with a hydraulic lock. Horizontal cylinder, cylinder diameter 90mm, stroke 300mm.

3. Trolley running

The trolley travels with motor drive, the running speed is 6.7m/min, and the traction is 39.13kN. 2 sets of Y112M-6 (2.2kW) motor, rated speed 940 rev / min; reducer model is DWPA147, speed ratio is 60:1; chain drive speed ratio is 2.932:1; wheel diameter is 400mm.

The above is the relevant introduction of the technical parameters of the tunnel lining formwork. At the same time, the above introduction is believed to make it easier and safer to use the tunnel lining formwork in the future.

What are the operational requirements for tunnel lining trolleys?

The tunnel concrete maintenance formwork

The personnel who need to operate the tunnel lining trolley need some specific understanding. Now many operators do not have this understanding, so many people now have the problem that the operator will use the product for a long time. The body has received a lot of damage, so the person using this product needs special attention.

Basic requirements

1. Personnel clothing should be regular, compact and neat, ensuring flexible hands and feet during work. Should not wear shoes with spikes, high heels, slippers, sandals or slippery shoes.

2. Winter clothes are not too thick, leggings should be tight, hats have ear holes, gloves are divided into five fingers, depending on weather and environmental pollution, wear glasses.

3, personnel should concentrate on their work, banned driving after drinking, prohibiting the carrying of books, newspapers, magazine novels, snacks and other items on the train.

4. When passing through bridges, tunnels, crossings or crossing lines, it must be “one stop, two look, three pass.” In the long bridges and tunnels, it is necessary to open the interval, and when the car arrives, it will be scattered to the shelter and the shelter. To ensure personal safety.

5. In the station to choose a wide area to walk, across the line is to ban the pedals, rails and slides, pay attention to the vehicles and lines on the lines, conduits and so on.

6. It is strictly forbidden to jump, drill or drive over the hook. The material should not be transferred under the tunnel lining trolley and on the coupler. When staying around the vehicle, the distance should be no less than 5 meters, and pay attention to the vehicle dynamics and whether there is a train on the adjacent line.

7. On the way to the reciprocating work site, the person in charge of construction should lead the road or the roadside. The double-track section should face the direction of the train, and should be separated from each other to avoid mutual collision. It is strictly forbidden to walk the heart and walk the wood.

8. Protection should be provided for the unblocked adjacent line. When the vehicle is found or the guardian announces the signal, the neighboring line should be parked at a distance of 500 meters away from the car. After the next road, the station should be outside the limit. Pay attention to the falling objects on the car and the ropes to injure people.

9. Construction of the two-line section, strictly implementing the two-line avoidance system, must avoid the car on the shoulder of one side of the line, and should not avoid the car on the adjacent line and across the adjacent line.

10. Rain and snow weather Anyone is banned from lying under the car, rail or pillow wood, take a cool, rain and snow. It is strictly forbidden to take the locomotives that are running, and it is strictly forbidden to travel by car.

If the operator does not have this understanding when using the tunnel lining trolley, then the most serious results will lead to certain problems for the user’s body, and now many companies pay great attention to this, so the lining trolley is being carried out. Operators are trained to know some common sense issues during operation.

Tunnel lining trolley daily operation precautions

1. If you want to use the tunnel lining trolley before you need to find the relevant operation manual to carry out effective device setting, all the process should check whether each component has a solid link one by one, you should look at their device practice. The situation, after the device is installed, must also be tested again, to see if the rotation of the entire vehicle is sensitive, of course, there will be a variety of different means of installation when the device is practiced.

2. The time-division operator of the start switch should cooperate with some other vehicles to make the structure of the whole template reach a construction requirement. When the entire template reaches the construction requirements, the upper and lower templates will be precisely combined. The template of the entire tunnel lining trolley is closed. After the two templates are laid up and down, the concrete can be poured, and the concrete can be conveyed to the side of the relevant formwork trolley. Basically, the concrete can be poured better. Balanced by force.

3. After the tunnel lining trolley is demoulded, the work can be completed after the strength of the inverted concrete reaches a certain operational requirement.

Tunnel lining formwork installation process

The tunnel concrete maintenance formwork

Before the tunnel lining formwork is installed, it is necessary to level enough space at the hole. To lay the track, the track is best to face the hole so that the trolley can enter the hole. The crane is first hoisted with the gantry, and then the stencil is installed to finally install the hydraulic system and the power supply system. Since the trolleys are all connected by bolts and hinges, the installation is very convenient, just assemble them according to the drawings.

1. Select the installation location: According to the actual situation of the site, select the appropriate installation location, so that the trolley can enter the tunnel smoothly or enter the work surface.

(1) Installation outside the cave; large space, suitable for crane operation.

(2) Installation in the cave; the space is small, and the bolt lifting operation is required.

2. Level the site and lay the track. The site should be as flat and open as possible so that the installation can be carried out. The site is generally 20×30 meters, depending on the actual situation. (If the hole is installed, it needs to be 50 cm on the outside, 30 cm on both sides, and the length of the trolley is +3 meters long to facilitate the lifting operation. In order to successfully complete the installation task, it needs to be doubled at this position. The length of the trolley + 3 meters will be kept free of obstacles. When installing in the cave, it is necessary to set up bolts. The specific position is determined according to the technical department.

According to the trolley gauge requirements, the track is laid, the track requirements are straight, no obvious triangular pits, the joints are not wrong, the front and rear, left and right height difference <5mm, the center line is as close as possible to the tunnel center line, the error is <15mm, the track sleeper spacing Generally ≤ 0.5 m, and fastened with road spikes, the rail uses 38kg / m heavy rail.

3. Install the walking wheel frame assembly.

Use the lifting device (hand chain hoist or crane) to place the driving wheel frame and the driven wheel frame on the paved track and make temporary support. Adjust the distance between the front and rear wheel frames according to the center line of the bottom longitudinal beam, and use The principle of equal diagonality adjusts the correct orientation of the wheel carrier and flatten it.

4. Install the bottom stringer.

Hang the bottom stringer on the wheel frame that has been placed, and use bolts to add temporary support to check whether there is any change in the diagonal. If it is within the correct value, install the gantry.

5. Install the gantry.

Generally, the gantry monolithic assembly is assembled on the ground first. Then, one piece is hoisted at the opposite position of the bottom rail and temporarily fixed with bolts.

6. Install the lock beam, scissors support

In order to become an organic whole as soon as possible, the gantry is installed and the lock beam and the scissors support provided in each space are installed. Use the drop ball or eye view to adjust and correct. And tighten the bolts in time to form a complete skeleton.

7. Install various components such as jacking cylinders.

8. Lifting the lifting beam and installing the table beam.

First lift the table beam on the top lift cylinder, adjust the center distance and diagonal line, add temporary support, hoist the hanging beam on the table beam and fasten it with bolts.

9. Install the hanging beam column and top template.

When installing the top mold, it should start from the middle and extend to both ends. This can reduce the accumulated error. Install the first top mold in the middle. After checking the chord length and string height to meet the design standards, install the other top molds until the top mold is completed. Installation task.

10. For the stability of the trolley, all the diagonal braces and scissors support on the lifting beam are tightened at this time.

11. Install the side mold (using a crane or hand hoist).

After the top mold is inspected, the side mold can be installed. When installing the side mold, it should be installed symmetrically to prevent roll. If it is installed in the hole, the side mold should be transported into the hole before installation, and the template should be placed in the order. On the basis of the wall, in order to hoist. The side mold installation is adjusted, the surface is smooth, flat, the joints are free of faults, and the geometrical dimensions meet the design requirements, and the through beams can be installed.

12. Install the through beam and support system.

13. Install hydraulic and electrical systems.

If installed in a small hole, the walking electrical appliance must be installed before the trolley moves back and forth.

14. Installation accessories such as: railings, step ladders and work platforms, plugging plates and so on.

15. Check all fastening bolts.

16. No-load test, whether the electrical hydraulic system works normally.

17. Test whether the various actions of the trolley are flexible and accurate.

18. After passing the self-inspection, report to the user for acceptance.

19. If the acceptance is qualified, fill in the form, and both parties sign and put it into use.

What are the main points of tunnel secondary lining concrete pouring construction?

The tunnel concrete maintenance formwork

The second lining construction of the tunnel is also the secondary lining support method of the tunnel. The white point is that the concrete layer that we can see on the expressway is not subject to any force.

“Second lining” is a term used in tunnel construction. When the tunnel is excavated, it is moved forward along the face of the hand, and the four sides of the tunnel that has been dug afterwards need to be reinforced. “Second lining” refers to the work that needs to be continued for secondary reinforcement around the reinforced tunnel.

Key points for construction of secondary lining concrete in tunnel

1. A tunnel is a building built underground or under water or in a mountain, with railways or roads for motor vehicles. According to its location, it can be divided into three categories: mountain tunnel, underwater tunnel and urban tunnel.

2. A mountain tunnel that passes under a mountain or hill to shorten the distance and avoid large slopes; an underwater tunnel that passes through the river or the sea to cross the river or the strait; to adapt to the needs of the railway through the big city A city tunnel is crossed underground in the city. Among the three types of tunnels, there are many mountain tunnels.

(1) Before concrete mixing, the moisture content of sand and gravel should be determined and the amount of materials should be adjusted according to the test results, and the construction mix ratio should be proposed.

When mixing concrete mix, the cement quality deviation shall not exceed ±1%, the aggregate quality deviation shall not exceed ±2%, and the water and admixture quality deviation shall not exceed ±1%.

(2) Before the concrete is poured, the base gravel, dirt, and accumulated water in the foundation pit should be removed. It is strictly forbidden to pour the concrete dry mix into the foundation pit with accumulated water.

(3) Before pumping concrete, the cement slurry mixed according to the design mix ratio or the concrete lubrication pipe prepared by halving the aggregate should be used.

(4) Concrete should be transported by concrete mixer truck to ensure that there is no segregation, withdrawal, and mixing of debris during transportation.

(5) Stratified from bottom to top, alternating left and right, and symmetrically perfused from both sides to the vault. The height, order and direction of each layer should be determined according to factors such as mixing capacity, transportation distance, filling speed, temperature inside the cave and vibration. In order to prevent the displacement of the trolley caused by excessive pressure deviation on both sides during pouring, the height difference of the perfusion surface on both sides should be controlled within 50cm, and the casting speed should be controlled reasonably.

(6) Pouring concrete should be directly placed into the warehouse as far as possible. The conveying pipe section should be connected with the hose control nozzle and the casting surface. It should not directly flow to the surface of the waterproof board to the pouring position. The offset should be controlled at 1.2. Within m, to prevent segregation.

(7) During the construction process, the pump should be continuously operated and pumped continuously for construction. It is advisable to avoid “cold seam” caused by stoppage. If it is interrupted for any reason, the interruption time should be less than the initial setting time or remodeling time of the concrete before the concrete. When the allowable time is exceeded, it should be treated according to the construction joint: the concrete at the joint should be tapped before the initial setting, and Make the seam surface have a reasonable, even and stable slope. Concrete that has not been tempered and exceeds the initial setting time of the cement should be removed.

(8) When pouring the concrete to the working window 50cm, before the working window is closed, the residue and other debris in the vicinity of the window should be cleaned, the release agent should be applied, and the sealing agent should be closed to prevent the surface of the window from being uneven. The patch even leaks.

(9) The anti-arc part below the arch line of the tunnel lining is the difficult part of the pouring operation. The rafting performance, slump and tamping method should be controlled to reduce the bubble in the reverse arc and improve the surface quality of the lining.

(10) The mold temperature of concrete should not be lower than 5 °C in winter construction and should not be higher than 32 °C in summer construction.

(11) Concrete should be vibrated and vibrated with vibrators, and reliable measures should be taken to ensure that the concrete is compact. When vibrating, do not shift the formwork, steel bars, drainage facilities, embedded parts, etc.

(12) The top cover is connected to the conveying pipe by the top mold center top sealer, and the top cover is gradually pressed. When the observation hole on the stop plate has a slurry overflow, the mark is completed.

(13) When pouring the concrete lining of the arch, the grouting hole should be reserved in the vault, the spacing of the grouting holes should be no more than 3m, and the reserved holes in the range of each template trolley should be no less than 4.

The grouting filling of the vault should be carried out after the strength of the lining concrete reaches 100%. The strength of the injected mortar should meet the design requirements, and the grouting pressure should be controlled within 0.1 MPa.

(14) After the concrete pouring is completed, the abandoned concrete and garbage at the site shall be cleaned in time to keep the construction site clean and tidy.

Basic knowledge of tunnel lining

The tunnel concrete maintenance formwork

Tunnel lining and initial support refer to the inner lining constructed with concrete and other materials under the condition that the tunnel has been initially supported to achieve reinforcement support, optimize the route drainage system, beautify the appearance, and facilitate the setting of communication. The role of lighting, monitoring and other facilities to meet the requirements of modern highway tunnel construction. Due to the construction conditions of the tunnel and the limitation of the construction environment, the construction of the two-line waterproof concrete in the tunnel is more difficult than the construction of the open-air concrete.

First, the main role

The function of the tunnel lining varies with the surrounding rock. For the stable surrounding rock of I, the deformation of the surrounding rock and the initial support is small and it tends to be stable soon, so the tunnel lining is basically not subjected to the surrounding rock pressure. The main function is waterproof and storage, and the flat lining surface is also conducive to ventilation and beauty. For the hard surrounding rock which is basically stable in II, although the deformation of the surrounding rock and the initial support is small, the surrounding rock pressure of the tunnel lining is not Large, but considering the long-term operation of the tunnel during the long-term operation of the anchor steel corrosion, the surrounding rock relaxation zone is gradually compacted, the initial support quality is unstable and other factors, so the tunnel lining is applied to increase the support lining safety; for III- V surrounding rock, due to the soft and broken rock mass, as well as rheological, expansion pressure, groundwater, etc., or due to shallow burial, bias and construction, etc., the self-stability of surrounding rock is very poor, only relying on initial support is not enough To suppress the development of surrounding rock deformation, the tunnel lining applied at this time will bear a large part of the late surrounding rock deformation pressure.

Second, the basic requirements

1. The degree of adhesion between the initial support and the tunnel lining will have an impact on the stress state of the composite lining. When there is a gap between the support and the lining, especially the concrete filled in the vault is not dense in real time, the surrounding rock pressure of the arch is saddle-shaped, that is, the vault is small and the arch is large, and even the outer side of the lining is pulled.

2. When the support and the lining are tightly bonded at the beginning, the radial force and the tangential force can be transmitted between the two layers, which can be checked according to the overall structure. When a waterproof layer is provided between the two layers, the combined structure is used to check and only the radial load is transmitted.

3. In order to prevent water leakage in the cave, the deformation of the tunnel lining should be controlled during design.

4. If there is a gap between the support and the lining, it should be backfilled and compacted.

Third, the calculation of tunnel lining

Due to the layered application of the composite lining, the time should be considered, and the calculation can be carried out according to the viscoelastic-plastic finite element method; the composite lining can also be approximated by the elastoplastic theory or the eigen curve method; On-site measurement data and model test results, as well as composite lining design adopted by internal and external data: For the external rock of tunnel lining with 30%-50% surrounding rock pressure for II-V surrounding rock, calculate by load-structure model . It should be pointed out that due to the insufficiency of the research on the mechanism of the tunnel lining, and the geological conditions of the surrounding rock are ever-changing, it is difficult to calculate the tunnel lining accurately. It is recommended to use simple and practical calculation methods. For weak surrounding rock with complex geological conditions, the tunnel lining calculation results of the above several methods should be compared to determine a reasonable and simple calculation method.

Fourth, the determination of the time for tunnel lining

For surrounding rock with better self-stability, tunnel lining should be applied after the surrounding rock and initial support deformation are basically stable, and the following conditions should be met:

1. The displacement rate around the tunnel has a significant slowdown trend.

2. The displacement speed of 1 m above the arch and the middle of the side wall is less than 0.1-0.2 mm/d, or the sinking speed of the dome is less than 0.07-0.15 mm/d.

3. The displacement value before applying the tunnel lining should reach 80%-90% of the total displacement value.

4. The surface cracks of the initial support no longer continue to develop.

5. When it is still difficult to meet the above conditions when taking certain measures, the tunnel lining may be applied in advance and should be strengthened.

For shorter tunnels and better self-stability of surrounding rock, tunnel lining can be applied after the entire tunnel is penetrated in order to reduce the interference between the various processes.

Fifth, measures to strengthen tunnel lining

For the complex geological conditions, the self-stability of the surrounding rock is poor, or in the case of shallow buried, biased, expansive surrounding rock, when the deformation of the surrounding rock and the initial support is not stable, it needs to be applied as a tunnel lining in advance. At this time, the tunnel lining is subjected to a large surrounding rock pressure, so the following measures are needed to strengthen the tunnel lining:

(1) Change the shape of the lining to adapt to the surrounding rock pressure, reduce the bending moment of the lining, and make the lining section basically under pressure.

(2) Improve the concrete marking, or use reinforced concrete, steel fiber concrete and other materials that can improve the bending strength.

(3) Applying the invert arch to form a closed structure for the lining to improve the overall rigidity of the structure and reduce the deformation of the surrounding rock.

(4) Measures such as advanced support and grouting to strengthen surrounding rock to increase the strength of the rock mass and improve the overall stability of the surrounding rock.

Tunnel lining formwork safety operation procedures

Double-track railway lining trolley

Tunnel lining formwork is a special equipment that must be used in the secondary lining of tunnel construction process. It is used for lining construction of the inner wall of the tunnel. There are mainly simple lining trolleys, full hydraulic automatic walking lining trolleys and grid-type lining trolleys. Tunnel lining formwork should follow the corresponding safety procedures during the construction process.

First, the operator’s job requirements

1. The operator should do a good job in the inspection and maintenance of the daily use of the tunnel lining trolley, and make necessary records.

2. It is strictly forbidden to operate according to the safety technology and the corresponding operating procedures.

Second, the job conditions

1. The operator should have received good safety and technical training. Hold the certificate and work.

Third, pre-job preparation

1. After the lining trolley is assembled, each connecting screw should be inspected and tightened one by one, and can be put into use after being inspected and accepted by all parties.

2. Wear belts on the lining trolley. The operating parts should be covered with 5cm planks to prevent the workers from falling from high places. The trolleys are equipped with eye-catching reflective strips.

Fourth, the safety procedures

1. The base surface of the lining trolley track should be solid and flat. It is strictly forbidden to be soft on the side and the top surface of the track should be on the same plane. The track pitch is consistent with the wheel edge of the platform.

2. The top surface of the lining trolley track is basically parallel with the longitudinal excavation surface of the tunnel. When the slope is large, the railing device should be installed at a position of not less than 3m at the track head to prevent the lining trolley from derailing during operation.

3. When the lining trolley moves in position, when there is automatic downward sliding, the operator should select an experienced person to operate, and send people on both sides of the forward direction to check the operation. When an abnormal situation occurs, the operator is notified at any time. Immediately brake the lining trolley. When the external force (loader, excavator) moves, it is necessary to use a qualified wire rope to drag along the uphill direction of the tunnel, slowly slide and move, let it move under the action of gravity, and it is strictly prohibited to lining the trolley in the direction of the slope.

4. The trolley should be slow and stable during the movement. When the movement is difficult, it should be carefully checked whether there are hard objects stuck on the two sides or the bottom of the trolley. Check whether there are steel intrusion restrictions on both sides and the top surface to hinder the running of the trolley. The trolley should be stopped, and the collapse of the steel skeleton will occur.

5. After the trolley is positioned, the operator should first wedge the wheel with a wooden wedge and then adjust the trolley under the command of the surveying personnel. When the offset of the trolley is large, the cylinder should be adjusted symmetrically. Make the trolley position reach the balance requirement. When the positioning of the trolley meets the requirements, the screw jacks on the bottom of the trolley should be tightened first, and then the jacks on both sides of the trolley should be screwed tightly. When the tops of the trolleys are tightened in place, the hydraulic cylinders are loosened. Open to protect the cylinder.

6. Before pouring concrete, the operators should check the jacks one by one to ensure that each screw jack is tightened and the top of each hydraulic jack is relieved. In the process of concrete pouring, it should be strictly symmetrically poured. The height difference between the concrete on both sides should not exceed 1 m, 0.5-0.8 m is appropriate, and the jack should be sent to check. When the concrete structure is thick and the square is large, the pouring speed should be slowed down in a timely manner, and the frequency of the mold should be tightened to prevent accidents such as running, rising and falling.

7. The power supply control box of the trolley should be placed on the base surface of the tunnel. It is strictly forbidden to install the control electric box on the trolley. All the power cords must pass through the leakage protector. The action current should not exceed 30MA, and the action time should not exceed 0.1S. The cable must be made of rubber flexible cable, and there must be no joints or damage in the middle. The frame body must have a reliable protection and zero connection.

8. The lighting on the trolley should use an electric voltage or a flashlight.

Five, other matters needing attention

1. When a vehicle passes under the clearance of a trolley during construction, it shall be assigned to conduct traffic command and management to prevent vehicles from colliding with the trolley.

2. Strictly control the center line of the rail to avoid excessive deviation between the center of the backstage vehicle and the center of the tunnel.
3. During the laying process of the rails, the rails and rails must be firmly connected to avoid the rails being crushed or the trolleys derailed during the running.

4. Remove the imaginary underneath the sleeper to avoid sinking due to the weight of the raft and the trolley.

5, the head plate is stressed, the reinforcement must be reinforced in the process of standing, in the process of pouring, there are people to see, strengthen at any time.

6. The second lining is poured for a long time. In order to facilitate the simultaneous construction of the second lining and the shovel, the pump is placed away from the lining trolley.

7. The conveying pipe is fixed firmly on the gantry. The pipe should not be in contact with the stencil, so as to avoid strong vibration at the nozzle when the squeezing is pressed out, so that the stencil can be deformed and run. The joint pipe clamps should be connected firmly to avoid explosion. The pipe squares are raised above the ground. When passing through the trolley, the pipe clamps are not in direct contact with the trolley components.